Case Study: Efficient Management of Wastewater Treatment Plant Sludge
The Solution
In collaboration with UMPS, BNL reviewed various industrial filtration technologies and selected TenCate Geotube® engineered textiles and Smartfeed™ chemical conditioning technology to address the challenges of wastewater treatment plant sludge dewatering.
BNL project manager William Chaloupka, PhD, was impressed by how closely the filtration testing of the sludge, using Rapid Dewatering Test (RDT) and Pressure-Geotube® Dewatering Test (P-GDT), characterized full scale operation.
The sludge was pumped by BNL-owned equipment and operators using a 6” centrifugal pump to convey the sludge through hard piping to the Smartfeed™ trailer.
The SmartFeed™ filtration manager monitored ph and chemical dose operations using parameters programmed into the SmartFeed™ trailer based on pilot testing results.
Geotube® containers were installed in existing sand filter beds with 6” piping fed from the SmartFeed™ processing trailer. Project parameters were monitored using a computer interface, allowing the filtration manager to optimize the process throughout the project. The SmartFeed™ data management software provided daily reports for project benchmarking.
*Geotube® is a registered trademark of TenCate™ and is used with permission.
**SmartFeed™ is a patent-pending technology of Mineral Processing Services, LLC.
Leverage UMPS’ Expertise for Wastewater Treatment Plant Sludge Removal
As demonstrated in our successful collaboration with BNL, our team of experienced engineers and specialists can develop a tailored tailing dewatering plan that addresses the unique challenges of your wastewater treatment plant. Reach out today or contact James Meagher to discuss your wastewater treatment plant dewatering needs and explore how we can help you optimize your operations.
Questions?
Contact James E. Meagher
207-741-2955
207-751-4416 (cell)
860-767-8256 x. 136 (office)